About Colonial Fox Theatre Foundation

Restoration Vision

Mission and Vision

Programs & Events

Newsletter

Memories

Trustees

Staff

History at a Glance

History

Annual Reports

Home / About Us / Progress Updates /

Progress Updates 2016

UPDATE: Restroom Plumbing Progress
December 30, 2016

UPDATE: Sprinkler System Progress

December 30, 2016

UPDATE: Hot Water Tank Installation
December 29, 2016

UPDATE: Sprinkler System Progress

December 27, 2016

UPDATE: Fire Safety Sprinkler System Progress

December 21, 2016

UPDATE: Restroom Mirror and Trim Installation

December 21, 2016

UPDATE: Restroom Hardware and Door Closer Installation
December 20, 2016

UPDATE: Restroom Counter Top Progress

December 14, 2016

UPDATE: Restroom Trim and Door Installed

December 8, 2016

UPDATE: Restroom Trim and Door Installation
November 29, 2016

UPDATE: Restroom Trim

November 21, 2016

UPDATE: Cutting into the Restroom Vanity Frame
November 16, 2016

UPDATE: Welding Restroom Vanity Frame

November 15, 2016

UPDATE: Restroom Wall Preparation for Base Tile
November 1, 2016

UPDATE: Restroom Progress

October 28, 2016

UPDATE: Plaster Work on Restrooms

October 7, 2016

UPDATE: Plaster Work on Restroom Walls and Ceiling Continued

September 27, 2016

UPDATE: Plaster Work on Restroom Walls and Ceiling
September 23, 2016

UPDATE: Plaster Work on Restroom Door Frames Update
September 22, 2016

UPDATE: Plaster Work on Restroom Door Frames Continued

September 21, 2016

UPDATE: Plaster Work on Restroom Door Frames

September 20, 2016

UPDATE: Restroom Plaster Continued

September 14, 2016

UPDATE: Restroom Lathe Repair
September 8, 2016

UPDATE: Restroom Plaster

September 6, 2016

UPDATE: Roughing in Restroom Electrical
August 17, 2016

NEWS: Old Artifacts Found in the Theatre
August 2, 2016

UPDATE: Beginning of Ventilation and Exhuast Install
July 28, 2016

UPDATE: Continued work on Roof Top Units
July 26, 2016

UPDATE: Pouring Restroom Floor

July 19, 2016

UPDATE: Calculating Sound Supressors for the HVAC units

July 19, 2016

UPDATE: Installing Extra Bracing for the Roof Top Units

July 14, 2016

UPDATE: Additional Steel Beams Transported to the Roof for HVAC Units (VIDEO)
July 13, 2016

UPDATE: Additional Steel Beams Lifted to Roof for HVAC Units
July 13, 2016

UPDATE: Plumbing in the Mens Restroom

July 1, 2016

UPDATE: Additional Steel Beams Lifted to Roof for HVAC Units
July 13, 2016

UPDATE: Plumbing in the Mens Restroom

July 1, 2016

UPDATE: Drilling New Sewer line for Restrooms
June 30, 2016

UPDATE: Windows Going Back into Place(VIDEO)

June 28, 2016

UPDATE: Windows Going Back into Place
June 28, 2016

UPDATE: Scaffolding Removed
June 28, 2016

UPDATE: Continued HVAC Work
June 28, 2016

UPDATE: Removal of Scaffolding
June 27, 2016

UPDATE: HVAC Units Placed on the Theatre
June 27, 2016

UPDATE: Roof Patch Complete

June 24, 2016

UPDATE: Truss Pocket Repair

June 24, 2016

UPDATE: Rehanging the Curtain

June 24, 2016

UPDATE: Raising the Curtain Track
June 24, 2016

UPDATE: Pulling Wire for HVAC

June 24, 2016

UPDATE: Cosmetic Cover for C Channel

June 23, 2016

UPDATE: Membrane Installation on Steel Beams

June 17, 2016

UPDATE: Last look at the Open Truss

June 15, 2016

UPDATE: HVAC Unit Roof Openings
June 15, 2016

UPDATE: Insulating the Proscenium Wall

June 14, 2016

UPDATE: HVAC Registers and Return Frame
June 14, 2016

UPDATE: Lowering the Center Jack supporting the Trusses(Video)
June 10, 2016

UPDATE: Removing Jacks for Truss Alignment
June 10, 2016

UPDATE: Working On Roof Curbs for RTU Beams

June 10, 2016

UPDATE: Welding Cross Braces for RTU Beams

June 10, 2016

UPDATE: Anchoring the C Column

June 7, 2016

UPDATE: Restroom Floor Demolition

June 7, 2016

UPDATE: Rebuilding Parapet Wall
June 7, 2016

UPDATE: Backup Truss Support

June 7, 2016

UPDATE: New Conduits and Chase

June 7, 2016

UPDATE: Pulling Electrical Wires

June 7, 2016

UPDATE: Electrical Bracket Installation
June 6, 2016

UPDATE: Setting the C Channel(Video)
June 3, 2016

UPDATE: Setting the C Channel

June 3, 2016

UPDATE: Electrical Brackets Installation

June 3, 2016

UPDATE: Installation of Steel Trusses

June 2, 2016

UPDATE: Restroom Demolition

June 2, 2016

UPDATE: Proscenium Steel Work

June 1, 2016

UPDATE: Proscenium Arch Supports

June 1, 2016

UPDATE: HVAC Duct Work

June 1, 2016

UPDATE: Hanging the First HVAC Duct

May 27, 2016

UPDATE: Rebuilt Proscenium Arch

May 26, 2016

UPDATE: Steel Trusses for the Proscenium Arch

May 26, 2016

UPDATE: HVAC Ducts Delivery

May 26, 2016

UPDATE: Demolition of Restroom Ceiling
May 23, 2016

UPDATE: Finishing the Attic Catwalks

May 23, 2016

UPDATE: Hanging HVAC Brackets

May 23, 2016

UPDATE: Installation of the Attic Insulation

May 23, 2016

UPDATE: Insulation Delivery
May 23, 2016

UPDATE: New South Attic Entrance

May 20, 2016

UPDATE: Platform Inside Proscenium Sail Wall

May 20, 2016

UPDATE: Straightening the Trusses

May 20, 2016

UPDATE: Drypacking the Beam Footings

May 20, 2016

UPDATE: Scaring the Bolt's Thread to Secure Steel Beams

May 20, 2016

UPDATE: Attic Cleared of Old HVAC

May 20, 2016

UPDATE: Building Secondary Deck Above the Proscenium Arch
May 19, 2016

UPDATE: CDL HVAC Demolition

May 19, 2016

UPDATE: Painting the Steel I Beams

May 18, 2016

UPDATE: CDL Heat & Air Removes Old Duct Work with Eby Construction
May 17, 2016

UPDATE: Steel Beams in Place with Water Protection for the Roof Pockets

May 17, 2016

UPDATE: Steel Beams Set with Birds Eye View(VIDEO) 

May 16, 2016

UPDATE: Steel Beams Lifted into Place(VIDEO) 
May 16, 2016

UPDATE: Beam Delivery and Mobilization 

May 11, 2016

UPDATE: Catwalk Cross Aisles

May 11, 2016

UPDATE: Roof Pockets for Steel Beams
May 11, 2016

UPDATE: Cutting Pockets into the Parapet Wall for Steel Beams  

May 10, 2016

UPDATE: Jacking the Upper Beam of the Prosceinum Truss to Level 
May 10, 2016

UPDATE: Attic Demolition for HVAC 

May 9, 2016

UPDATE: Building Proscenium Arch Supports  
May 5, 2016

UPDATE: Parapet Wall Prep for RTU Beams 

May 5, 2016

UPDATE: Trusses to be Structurally Supported

May 3, 2016

UPDATE: Launching Phase 6  
April 27, 2016

NEWS: Way Down Wanderers Concert  
April 23, 2016

UPDATE: Grand Reveal of the Entryway 
April 21, 2016

NEWS: Entryway Reveal Feature Presentation 
April 21, 2016

UPDATE: Pre-Bid Conference for Phase VI was hosted yesterday, March 22, 2016.  March 23, 2016

UPDATE: Phase VI Plans published for bid closing on April 7, 2016
March 9, 2016

UPDATE: SHPO approves VI Plans
March 9, 2016

UPDATE: Floor Tile Installation
February 8, 2016

UPDATE: Tile Installation
January 6, 2016

2015 Progress Updates

2014 Progress Updates

2013 Progress Updates

2012 Progress Updates

2011 Progress Updates

2010 Progress Updates

2009 Progress Updates

2008 Progress Updates

2007 Progress Updates

2010 - 1920 Progress Updates Archive

 

Become a Fan

Donate / Renew

restoration vision

Visit Other Kansas Historic Theaters

Contact Us

Theater Tours

 

 
Follow us on Twitter Find us on Facebook